The current gas and electricity supply
contracts used by Buckinghamshire County Council (BCC) are due to
expire on 30 September 2020 and require renewing. BCC currently
purchases its gas and electricity through the LASER ‘flexible
procurement’ framework which allows forward purchasing of
energy when wholesale market prices are low. It is recommended that
BCC renews the gas and electricity supply contract through the
current LASER framework. However, a departure from the normal 4
year contract period is recommended to be replaced with a 2 year
contract, with two further 1 year extension periods allowed (to a
maximum of 4 years). This is to ensure the future Buckinghamshire
Council is able to change contracting approaches mid-contract if
necessary.
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 04/07/2019
Decision due: 29 Jul 2019 by Cabinet Member for Planning and Environment, Cabinet Member for Resources
PE07.19
Lead member: Cabinet Member for Planning and Environment, Cabinet Member for Resources
Contact: Martin Dickman, Environment Services Director Email: mdickman@buckscc.gov.uk Tel: 01296 382850.
Decisions
- 15/07/2019 - Procurement of electricity & gas supplies for 2020-2022 (Decision to be taken)
- 23/07/2019 - Procurement of electricity & gas supplies for 2020-2022 (Decision taken)
Documents